Witch Creek Fire Street Improvements consists of overlay of approximately 2.3 miles of existing roadway with asphalt concrete (AC) pavement and make roadway subgrade repairs where needed. The project will also remove and replace existing sidewalks with Americans with Disabilities (ADA) compliant sidewalks, install and replace curb ramps with ADA-compliant curb ramps, remove and replace curbs and gutters, remove and replace existing damaged cross gutters, and restripe roadways.
|
|
Jaro, Janice
|
|
5
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$5,260,001
|
Construction Activity
|
(1)
|
$3,949,063
|
(3)
|
Fully Funded
|
|
Ramona Paving, Inc
|
(1)
|
19 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|