The City of San Diego Project Information Details
6118 Caminita Sacate SD Emergency
(Emergency (Std, as-needed) Project)
The City of San Diego
Project Information Details
6118 Caminita Sacate SD Emergency
(Emergency (Std, as-needed) Project)
Print Page  
General Information
B23004 (Storm Water Drainage Asset)
Emergency repair of approximately 100 linear feet of a 25-inch CMP storm drain located in the City easement at 6118 Caminito Sacate
Choi, Jong
7
NAVAJO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $1,750,000
Construction Activity
(1) $1,500,000
(3) Fully Funded
Cass Construction, Inc.
(1) 21 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024