General Information
B23042 (Sewer Asset)
Rehabilitate approximately 22,377 LF (4.24 miles) of existing 8-in sewer mains, including 12 external point repairs that require trenching, 6 internal point repairs that do not require trenching, rehabilitation of 23 manholes, installation of 1 new manhole, install 27 new cleanouts, rehabilitation of existing sewer laterals, and installation of sewer lateral cleanouts at the property line, if needed.
The project is located in council district 5, within the Rancho Bernardo community.
Ramos-Banuelos, Jaime
5
RANCHO BERNARDO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $11,287,169
Construction Activity
(1) $5,293,648
(3) Partially Funded
Burtech Pipeline, Incorporated
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024