The City of San Diego Project Information Details
Redwood Village/Rolando Park Imp 1A (W)
(Job Order Contract Project)
The City of San Diego
Project Information Details
Redwood Village/Rolando Park Imp 1A (W)
(Job Order Contract Project)
Print Page  
General Information
B23047 (Water Asset)
Construction of Redwood Village/Rolando Park Improv 1A consists of the abandonment of approximately 3201 linear feet of existing water mains, and the installation of 3477.07 linear feet of 12-inch water mains, including all associated water services, fire hydrants, valves, water mains, and other appurtenances. All other work and appurtenances will be included in this project area in accordance with these specificiations and these drawings numbered 0100594-D.
Ramos-Banuelos, Jaime
9
MID-CITY:EASTERN AREA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $3,695,340
Construction Activity
(1) $2,239,473
(3) Fully Funded
Burtech Pipeline, Incorporated
(1) 16 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024