B23047
(Water Asset)
|
Construction of Redwood Village/Rolando Park Improv 1A consists of the abandonment of approximately 3201 linear feet of existing water mains, and the installation of 3477.07 linear feet of 12-inch water mains, including all associated water services, fire hydrants, valves, water mains, and other appurtenances. All other work and appurtenances will be included in this project area in accordance with these specificiations and these drawings numbered 0100594-D.
|
|
Ramos-Banuelos, Jaime
|
|
9
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$3,695,340
|
Construction Activity
|
(1)
|
$2,239,473
|
(3)
|
Fully Funded
|
|
Burtech Pipeline, Incorporated
|
(1)
|
16 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|