B23049 (Water Asset)
The purpose of this project is to provide design services to build the infrastructure required to continue discharging sedimentation basin residuals to Miramar Reservoir from the time Pure Water Program is commissioned until the “long-term” residuals project at MWTP is constructed.
Ammerlahn, Parita
5
SCRIPPS MIRAMAR RANCH
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $5,612,453
Construction Activity
(1) $4,409,785
(3) Partially Funded
To Be Selected
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.