The City of San Diego Project Information Details
Miramar WTP Interim Solids Management
(Design Bid Build Project)
The City of San Diego
Project Information Details
Miramar WTP Interim Solids Management
(Design Bid Build Project)
Print Page  
General Information
B23049 (Water Asset)
The purpose of this project is to provide design services to build the infrastructure required to continue discharging sedimentation basin residuals to Miramar Reservoir from the time Pure Water Program is commissioned until the “long-term” residuals project at MWTP is constructed.
Ammerlahn, Parita
5
SCRIPPS MIRAMAR RANCH
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $5,612,453
Construction Activity
(1) $4,409,785
(3) Partially Funded
To Be Selected
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 10/01/2024