Project Information Details
Black Mountain Reservoir Spillway Stairs
(Design Bid Build Project)
Project Information Details
Black Mountain Reservoir Spillway Stairs
(Design Bid Build Project)
Print Page
General Information
Project Identification Number:
B23110
(Water Asset)
Project Description:
The scope of work for this project is to create safer access to the Black Mountain Reservoir spillway energy dissipating structure and outlet discharge portal for inspection and maintenance per the request of the Division of Safety of Dams (DSOD). The following scope is based on DSOD and PUD recommendations:
• Clear and grub vegetation for the proposed construction of the staircase.
• Construct path and stairs with dual or single handrail from the top of the slope to the spillway portal.
Contact Person:
Choi, Jong
Council District(s):
5
Community Area(s):
BLACK MOUNTAIN RANCH
Project Location Map:
Click Here
Estimated Project Schedule
(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
Estimated Project Dollar Amount
(1)
A. Total Project Cost:
(1)
$700,000
Construction Activity
A. Estimated Construction Contract Amount:
(1)
$350,000
B. Funding Status:
(3)
Partially Funded
C. Contractor:
To Be Selected
D. Expected Contract Duration:
(1)
Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502
Updated As Of:
12/01/2024