The City of San Diego Project Information Details
5505 Morehouse Dr SD Emergency
(Emergency (Std, as-needed) Project)
The City of San Diego
Project Information Details
5505 Morehouse Dr SD Emergency
(Emergency (Std, as-needed) Project)
Print Page  
General Information
B23116 (Storm Water Drainage Asset)
Replace failed 36-inch CMP storm drainpipes and adjacent structures, restoration of the slope and paved parking area impacted by the sinkhole.
Choi, Jong
6
MIRA MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $1,170,000
Construction Activity
(1) $1,280,583
(3) Fully Funded
TC Construction Co., Inc.
(1) 4 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024