|
|
Project Information Details
AC Overlay Group 2303
(Design Bid Build Project)
|
|
Project Information Details
|
AC Overlay Group 2303
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B23156
(Transportation Asset)
|
This project will resurface approximately 2.86 miles of existing roadways by installing new AC pavement, ADA compliant curb ramps, sidewalk panels, curb and gutter, pedestrian push buttons and posts, pedestrian barricades, protective railings, and replacing inlet markers, roadway subgrade material for base repairs, traffic striping, and vehicular detector loops for various streets throughout the City.
|
|
Jaro, Janice
|
|
1, 8, 9, 2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$4,828,600
|
Construction Activity
|
(1)
|
$3,273,925
|
(3)
|
Fully Funded
|
|
ATP Engineering Contractors
|
(1)
|
10 Months
|
|
|
See B23157 for Transportation Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|