|
|
Project Information Details
Point Loma Heights Improv 3 (W)
(Design Build Project)
|
|
Project Information Details
|
Point Loma Heights Improv 3 (W)
|
(Design Build Project)
|
Print Page
|
General Information
|
|
B24048
(Water Asset)
|
Replace approximately 11,256 LF (2.13 mi) of existing 4-, 6-, 8-, and 12-inch asbestos cement (AC) and polyvinyl chloride (PVC) mains with appropriately sized mains.
|
|
Narvaez, Rex
|
|
2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$13,142,000
|
Design-Build Activity
|
(1)
|
$8,487,000
|
(3)
|
Partially Funded
|
|
To Be Selected
|
(1)
|
Duration to be determined.
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
12/01/2024
|
|
|