B24065
(Storm Water Drainage Asset)
|
This emergency repair project will replace-in-place approximately 30 linear feet (LF) of 24-inch diameter corrugated metal pipe (CMP) storm drain with new 24-inch diameter reinforced concrete pipe (RCP) adjacent to the east side of the structure, and line approximately 90 LF of existing 24-inch diameter RCP storm drain between the curb inlet on Sutter Street and the existing outfall structure at the south end of the property.
|
|
Choi, Jong
|
|
3
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$538,000
|
Construction Activity
|
(1)
|
$350,000
|
(3)
|
Fully Funded
|
|
Orion Construction
|
(1)
|
5 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|