B24068
(Storm Water Drainage Asset)
|
Repairs will include but are not limited to installation of temporary storm drain bypass during rain events, replacement of the existing failed 18-inch diameter corrugated metal pipe (CMP) storm drain with new 18-inch diameter reinforced concrete pipe (RCP). Following completion of work, all areas impacted by the emergency will be restored to their pre-impact condition, including revegetation and erosion control of the excavated area.
|
|
Choi, Jong
|
|
4
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$750,000
|
Construction Activity
|
(1)
|
$500,000
|
(3)
|
Fully Funded
|
|
TC Construction Co., Inc.
|
(1)
|
8 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|