|
|
Project Information Details
Guy St Water Main Replacement
(Job Order Contract Project)
|
|
Project Information Details
|
Guy St Water Main Replacement
|
(Job Order Contract Project)
|
Print Page
|
General Information
|
|
B24072
(Water Asset)
|
This project will replace approximately 408 linear feet (0.08 miles) of an existing 6” diameter asbestos cement (AC) water main with a new 8” diameter polyvinylchloride (PVC) water, including all associated water services, fire hydrants, valves, and other appurtenances. The project also proposes to replace and install four new curb ramps at the intersection of Guy St & Pringle St.
|
|
Ramos-Banuelos, Jaime
|
|
3
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$1,718,051
|
Construction Activity
|
(1)
|
$1,718,051
|
(3)
|
Fully Funded
|
|
Palm Engineering Construction Company, Inc.
|
(1)
|
8 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|