General Information
B24144 (Storm Water Drainage Asset)
Work consists of but is not limited to replacement of approximately 65 LF of failed 18-RCP storm drain pipe with 125 LF of 18-inch RCP. Work will also include installation on new cleanout box, and energy dissipater at the end of the new storm drain. Work area to be revegetated after completion of construction.
Choi, Jong
7
NAVAJO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $4,000,000
Construction Activity
(1) $2,750,000
(3) Fully Funded
Cass- Arrieta
(1) 17 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.