General Information
B25006 (Transportation Asset)
Work will involve furnishing all labor, materials, equipment, services, quality assurance and construction including but not limited to grinding, cold milling, hauling and disposal of existing asphalt, concrete and installment of new pavement and excavation for pavement base repairs.
Gibson, William
3
DOWNTOWN, GREATER GOLDEN HILL
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $6,500,000
Construction Activity
(1) $6,200,000
(3) Partially Funded
To Be Selected
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.