Project Information Details
5989 San Dimas Ave USD SD Emergency
(Sole Source Emergency Project)
|
|
Project Information Details
|
5989 San Dimas Ave USD SD Emergency
|
(Sole Source Emergency Project)
|
Print Page
|
General Information
|
|
B25028
(Storm Water Drainage Asset)
|
The Work consists of but is not limited to replacement of approximately 340 linear feet (LF) of 24-inch corrugated metal storm drain pipe (CMP) with 24-inch Reinforced concrete pipe (RCP). Work will also include new cleanout structure and energy dissipater. Disturbed area to be revegetated after construction. Contractor will procure consultant to provide Design and Construction Support services necessary to complete the required work for the project.
|
|
Choi, Jong
|
|
7
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$4,000,000
|
Construction Activity
|
(1)
|
$2,700,000
|
(3)
|
Partially Funded
|
|
TC Construction Co., Inc.
|
(1)
|
Duration to be determined.
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
03/01/2025
|
|
|