City Logo
Print Page
Montezuma TS 06/13 EPA
 
General Information
S00332
Increase capacity of Montezuma Trunk Sewer by upsize existing 12" & 15" to 18" & 21" sewer.
Spier, Carl
Construction
 
Construction Schedule
July 2012
August 2014
 
Cost
$5,814,000
 
Website Comments
None
 
08/01/2014
The cost and schedule data shown here are the City’s current best estimate and subject to change. Changes (if any) are updated once a month.