The City of San Diego Project Information Details
Beyer Park Development
(Design Bid Build Project)
The City of San Diego
Project Information Details
Beyer Park Development
(Design Bid Build Project)
Print Page  
General Information
S00752 (Parks Asset)
This project provides for design and construction of a new 8-acre park on an approximately 43-acre site located in the San Ysidro Community, Council District 8. Amenities will include multi-purpose fields, children's play area, picnic areas, comfort station, basketball court, dog park, skate park, and walking trails.
Genova, Darren
8
SAN YSIDRO, OTAY MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $22,446,340
Construction Activity
(1) $17,066,340
(3) Fully Funded
Dick Miller, Inc.
(1) 17 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.