City Logo
Print Page
University Ave Pipeline Replacement
 
General Information
S11021
This project replaces 23,072 linear feet (4.3 miles) of existing cast iron transmission and distribution water mains with new 16-inch PVC pipeline. This project includes the replacement of pedestrian curb ramps to comply with ADA requirements, restoring street surfaces, striping, revegetation, and landscaping of impacted areas during construction.
Asgharzadeh, Iraj
Construction
 
Construction Schedule
April 2015
July 2018
 
Cost
$26,000,000
 
Website Comments
None
 
05/01/2015
The cost and schedule data shown here are the City’s current best estimate and subject to change. Changes (if any) are updated once a month.