The City of San Diego
Project Information Details
30th Street Pipeline Replacement
Print Page  
General Information
S12010 (Water Asset)
Otay1stPL:Segment cross I-805 run west along Polk St is repl w/ 30" CMLS PL & continuous from Boundary St to University Height Reservoir w/16"PVC PL.
Otay2ndPL:Repl w/42"CMLCS from Highland Ave & Polk Ave to Upas St & 30th St & exist parallel PL is repl w/12"PVC PL.
Otay2ndPL Extension: Repl w/ 36"CMLCS from Wightman St & Swift Ave to Polk St,continue w/24"CMLCS to University Heights Reservoirs. Segment cross I-805 is 36" CMLS. Segment along 33rd St is 30"CMLCS from Lincoln Ave to Polk Ave
Bose, Sheila
3,8
GREATER GOLDEN HILL; GREATER NORTH PARK; SOUTHEASTERN SAN DIEGO,SOUTHEASTERN
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $14,889,115
Construction/Design-Build Activity
(1) $10,323,300
(3) Fully Funded
To Be Selected
(1) 24 Months
 
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 06/01/2016