30th Street Pipeline Replacement
(Design Bid Build Project)
|
|
Project Information Details
|
30th Street Pipeline Replacement
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
S12010
(Water Asset)
|
The 30th Street Pipeline Replacement Project will replace approximately 5.15 miles of water main within the North Park, Golden Hill, and Southeastern communities. This project will also increase pedestrian access by installing curb ramps at several intersections throughout the project area. Project alignment runs along 30th Street from Polk Ave to Commercial Ave.
|
|
Ramos-Banuelos, Jaime
|
|
3, 8, 9
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$35,359,711
|
Construction Activity
|
(1)
|
$27,575,762
|
(3)
|
Fully Funded
|
|
Ortiz Corp
|
(1)
|
54 Months
|
|
|
See B13066 for Transportation Asset
Click Here
|
See B21019 for Transportation Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
03/01/2024
|
|
|