PACIFIC BEACH PIPELINE SOUTH (W)
Print Page  
General Information
S12015 (Water Asset)
This project proposes for replacement of 38,725 linear feet of ex. CI water main, and 6,731 linear feet of ex. VC sewer main to new 16-inch PVC mains alone with the abanonment of the Pacific Beach Reservior, which is no longer in use.
Batta, Nabil
2
LINDA VISTA; MIDWAY-PACIFIC HIGHWAY; MILITARY FACILITIES; MISSION BAY PARK; PACIFIC BEACH; PENINSULA; RESERVE
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $38,493,567
Construction/Design-Build Activity
(1) $30,952,405
(3) Fully Funded
TC Construction
(1) 46 Months
 
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.