The City of San Diego Project Information Details
Carmel Grove NP-Comfort Station
(Job Order Contract Project)
The City of San Diego
Project Information Details
Carmel Grove NP-Comfort Station
(Job Order Contract Project)
Print Page  
General Information
S16038 (Parks Asset)
This project provides for the design and construction of a new 350 SF pre-fabricated comfort station to serve the public and accessibility improvements at Carmel Grove Neighborhood Park to meet Federal, State and Local standards.
Lewis, Nikki
1
CARMEL VALLEY
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $2,553,500
Construction Activity
(1) $1,157,499
(3) Partially Funded
LDCO - Luan Dauti
(1) Duration to be determined.
Additional Remarks
None
See S16033 for Parks Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024