B13186 (Water Asset)
The installation of 160 LF (0.03 mi) of 8" water main replace-in-place (RIP), 65.76 LF (0.01 mi) of 12' (RIP), 4,989 LF (0.94 mi) of 16' (RIP), & 3,572.18 LF (0.67 mi) of abandoning replace in a new trench, & the installation 945.88 LF (0.18 mi) 12" of new water pipe in a new trench. Installation of water services, tees, cross, reducers, gate valves, trench shoring, resurfacing, curb ramps, traffic controls, and other work and appurtenances.
Sleiman, Alex
6, 7, 2
KEARNY MESA, CLAIREMONT MESA, MISSION VALLEY
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $4,993,103
Construction Activity
(1) $3,429,506
(3) Fully Funded
Burtech Pipeline, Incorporated
(1) 88 Months
Additional Remarks
None
See B14069 for Sewer Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.