The City of San Diego Project Information Details
Sewer & AC Water Group 776 (W)
(Design Bid Build Project)
The City of San Diego
Project Information Details
Sewer & AC Water Group 776 (W)
(Design Bid Build Project)
Print Page  
General Information
B13197 (Water Asset)
Replace approximately 6,877 linear feet of high priority AC water mains with new PVC water mains, including associated water services, fire hydrants, curb ramps and appurtenances. Project is located in Mid-City: Eastern Area, Council District 4.
Jaro, Janice
4
MID-CITY:EASTERN AREA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $2,875,000
Construction Activity
(1) $1,964,575
(3) Fully Funded
P K Mechanical System
(1) 43 Months
Additional Remarks
None
See B00387 for Sewer Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 10/01/2024