Project Information Details
Pacific Beach TS Interconnect Upgrade
(Job Order Contract Project)
|
|
Project Information Details
|
Pacific Beach TS Interconnect Upgrade
|
(Job Order Contract Project)
|
Print Page
|
General Information
|
|
B15065
(Transportation Asset)
|
Install 3" conduits, signal interconnect cables, removal of SIC termination cabinets and replacement with pull boxes and installation of 332 controller cabinets on existing foundation. Segments along Grand Avenue.,. Garnet Avenue., Ingraham Street, Mission Boulevard, Morena Boulevard, Cass Street, Fanuel Street and Mission Bay Drive.
|
|
Barhoumi, Zach
|
|
1, 7, 2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$2,819,219
|
Construction Activity
|
(1)
|
$1,204,430
|
(3)
|
Fully Funded
|
|
To be selected
|
(1)
|
13 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|