Project Information Details
AC Water & Sewer Group 1017 (S)
(Design Bid Build Project)
|
|
Project Information Details
|
AC Water & Sewer Group 1017 (S)
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B15116
(Sewer Asset)
|
This project will replace approx. 14,998' (2.84 miles) of existing 4", 6", and 12" asbestos cement and 4 and 6-in cast iron water mains. 477' to be trenchless horizontal directional drilling; approximately, 349' of 8" vitreous sewer line to be rehabilitated; 1417' of 8" asbestos water main to be abandoned; 838' of water pipe to be re-aligned; furthermore, ADA curb ramps will be upgraded where needed. added during construction of 503 feet rehab pipe.
|
|
Ramos-Banuelos, Jaime
|
|
2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$660,219
|
Construction Activity
|
(1)
|
$284,598
|
(3)
|
Fully Funded
|
|
Burtech Pipeline, Incorporated
|
(1)
|
59 Months
|
|
|
See B15119 for Water Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|