The City of San Diego Project Information Details
Morena Conveyance Northern
(Design Bid Build Project)
The City of San Diego
Project Information Details
Morena Conveyance Northern
(Design Bid Build Project)
Print Page  
General Information
B15141.2 (Sewer Asset)
The Morena Conveyance North project includes the installation of 48” 3.9 miles of 48-inch wastewater forcemain pipeline (approx. 20,870 LF) and 30-inch Welded Steel Pipe brine centrate/conveyance pipeline (approx.. 20,870 LF) from forcemain station 368+00 (Brine Centrate pipeline station 1034+32) north along Genesee Ave, east along Nobel Dr., north along Town Center Dr., east along Executive Dr., and underneath I-805 to the North City Water Reclamation plant. The work involves tunneling underne
Tadros, Sameh
6, 2
CLAIREMONT MESA, UNIVERSITY
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $133,104,520
Construction Activity
(1) $104,837,095
(3) Fully Funded
OHL Construction
(1) 52 Months
Additional Remarks
None
See B15141 for Sewer Asset Click Here
See B15141.4 for Sewer Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.