B16018
(Sewer Asset)
|
Replacement of 11,563 LF (.99 mi) of existing 6” – 24” CP & VC sewer mains which are included on the Wastewater Collection’s referral list and have been recommended for replacement. Included the replacement of associated sewer laterals, sewer manhole, curb ramps, and other appurtenances.
|
|
Ramos-Banuelos, Jaime
|
|
1, 3, 8, 7, 9, 2, 4
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$10,148,218
|
Design-Build Activity
|
(1)
|
$8,441,537
|
(3)
|
Fully Funded
|
|
TC Construction Co., Inc.
|
(1)
|
61 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|