The City of San Diego Project Information Details
ADA S/W Group 3E W Point Loma
(Design Bid Build Project)
The City of San Diego
Project Information Details
ADA S/W Group 3E W Point Loma
(Design Bid Build Project)
Print Page  
General Information
B16100 (Transportation Asset)
This project will provide a roundabout and missing sections of sidewalks and curb ramps at the Bacon Street & West Point Loma Boulevard intersection. The project will also construct a complete pedestrian path from Seaside Street to Valeta Street with a new curb inlet at the Nimitz Boulevard & West Point Loma Boulevard intersection.
Ashrafzadeh, Mastaneh
2
OCEAN BEACH
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $2,157,590
Construction Activity
(1) $974,414
(3) Fully Funded
Crest Equipment, Inc.
(1) 34 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 03/01/2024