The City of San Diego Project Information Details
Southcrest Green Infrastructure (GI)
(Design Bid Build Project)
The City of San Diego
Project Information Details
Southcrest Green Infrastructure (GI)
(Design Bid Build Project)
Print Page  
General Information
B16112 (Storm Water Drainage Asset)
The project scope of work includes capturing runoff from the four drainage areas and treat the 2-year storm.
The overall project feasibility required review and modification of the Drainage Management Areas (DMAs). DMA 1 (Z Park) was removed from the project scope because the location is designated park land and the use of this property for storm water treatment would require council action. Additionally, DMAs 3 and 4 were also removed due to design infeasibility. They were replaced with DMA 6
Straughn, Jayna
8, 4
SOUTHEASTERN SAN DIEGO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $5,698,405
Construction Activity
(1) $4,089,417
(3) Partially Funded
De La Fuente Construction, Inc.
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 10/01/2024