Mira Mesa South Storm Drain Replacement consists of the installation of 568 linear feet of 36-inch reinforced concrete pipe storm drain and the abandonment of 559 linear feet of 36-inch corrugated metal pipe storm drain. The project is located in the Mira Mesa community, council district 6.
|
|
Straughn, Jayna
|
|
6
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$2,364,903
|
Construction Activity
|
(1)
|
$739,736
|
(3)
|
Fully Funded
|
|
Blue Pacific Engineering and Construction
|
(1)
|
23 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|