Project Information Details
Market Street Water Pipe Replacement
(Design Bid Build Project)
|
|
Project Information Details
|
Market Street Water Pipe Replacement
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B17052
(Water Asset)
|
This project provides replacement of approximately 0.3 miles of existing AC water main and the associated appurtenances on Euclid Avenue between Naranja Street and Lakiba Palmer. This project is being bundled with the Market St Sewer Pipe Replacement (B17054) and Market St – 47th to Euclid Complete St (S16061) project.
|
|
Ashrafzadeh, Mastaneh
|
|
4
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$2,869,487
|
Construction Activity
|
(1)
|
$2,025,269
|
(3)
|
Fully Funded
|
|
Palm Engineering Construction Company, Inc.
|
(1)
|
29 Months
|
|
|
See B17054 for Sewer Asset
Click Here
|
See S16061 for Transportation Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|