The City of San Diego Project Information Details
Sewer Group 843
(Design Bid Build Project)
The City of San Diego
Project Information Details
Sewer Group 843
(Design Bid Build Project)
Print Page  
General Information
B17189 (Sewer Asset)
Replace approximately 6,491 linear feet (1.23 mi) of 6-, 8-, 10-, and 15-inch VC sewer mains with new PVC sewer mains. This project is located in CD 8; Otay Mesa-Nestor, San Ysidro, and Tijuana River Valley Communities.
Jaro, Janice
8
SOUTHEASTERN SAN DIEGO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $9,069,070
Construction Activity
(1) $6,580,616
(3) Fully Funded
Burtech Pipeline, Incorporated
(1) 38 Months
Additional Remarks
None
See B23093 for Transportation Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.