Project Information Details
Asphalt Resurfacing Group 1902
(Design Bid Build Project)
|
|
Project Information Details
|
Asphalt Resurfacing Group 1902
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B18135
(Transportation Asset)
|
The project involves furnishing all labor, materials, equipment, services and construction which include placement of asphalt overlay, replacing traffic signal detection loops and stub outs, adjustment of city manhole and gate valve covers, cold milling, pavement base repair, installation of curb ramps to meet ADA requirements, installation of pedestrian barricades at prohibited crossing movements, replacing/installing new ADA-compliant push buttons, street and sidewalk sweeping.
|
|
Lahmann, Joshua
|
|
Geo-Mapping is in progress
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$2,357,224
|
Construction Activity
|
(1)
|
$2,094,666
|
(3)
|
Fully Funded
|
|
ATP Engineering Contractors
|
(1)
|
16 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|