The City of San Diego Project Information Details
Tecolote North Parking Lot Improvements
(Design Bid Build Project)
The City of San Diego
Project Information Details
Tecolote North Parking Lot Improvements
(Design Bid Build Project)
Print Page  
General Information
B18231 (Parks Asset)
The adjacent parking lot is to be resurfaced and new accessible parking spaces and curb ramps installed. This may include a reconfiguration of the parking striping, revised planter islands (existing trees to be preserved), and storm water treatment BMPs. The path of travel from the parking lot to the playground will need to be modified to address accessibility. Either existing walkways will need to be removed and replace to address cross slope issues or a new path from the parking lot will nee
Oliver, Kevin
2
MISSION BAY PARK
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $869,000
Construction Activity
(1) $400,000
(3) Fully Funded
Dick Miller, Inc.
(1) 19 Months
Additional Remarks
None
See B19016 for Parks Asset Click Here
See B18232 for Parks Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 10/01/2024