|
|
Project Information Details
El Cajon & Kansas - Traffic Signal
(Design Bid Build Project)
|
|
Project Information Details
|
El Cajon & Kansas - Traffic Signal
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B19060
(Transportation Asset)
|
This project proposes to construct a new two-stage pedestrian traffic signal at the intersection of El Cajon Boulevard and Kansas Street to improve safety and operation. The improvements include installation of new two-stage pedestrian signal for EB & WB El Cajon Blvd including traffic signal poles, vehicle & pedestrian indications, ADA curb ramps,pedestrian countdown timers, ADA push buttons, detection, signal interconnect and EVPE. Enhance center S-median to create an ADA path for pedestrians
|
|
Zhang, Dayue
|
|
3
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$1,580,000
|
Construction Activity
|
(1)
|
$787,100
|
(3)
|
Fully Funded
|
|
To Be Selected
|
(1)
|
12 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|