City Heights Pool Reconstruction
(Design Bid Build Project)
|
|
Project Information Details
|
City Heights Pool Reconstruction
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B19068
(Parks Asset)
|
This project scope includes reconstruction of the main pool, slide, & decking area as well as children’s pool and slide replacement. To prevent structural damage from occurring in the future, the existing soil immediately surrounding the pool will be removed and replaced with more suitable material and an underground drainage system will be installed to pump nuisance water away from the site. New amenities include shade sails and accessibility upgrades (including the recreation center).
|
|
Van Martin, Debbie
|
|
9
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$7,205,786
|
Construction Activity
|
(1)
|
$4,791,777
|
(3)
|
Fully Funded
|
|
Fordyce Construction, Inc.
|
(1)
|
15 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|