The City of San Diego Project Information Details
University City Improv 1 (S)
(Design Bid Build Project)
The City of San Diego
Project Information Details
University City Improv 1 (S)
(Design Bid Build Project)
Print Page  
General Information
B19087 (Sewer Asset)
Replacement of approximately 7,930 LF (1.50 miles) of existing sewer mains, installation of approximately 771 LF (0.15 miles) of new sewer mains. The project is located in council district 1, University City community.
Sleiman, Alex
6
UNIVERSITY
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $7,426,457
Construction Activity
(1) $4,882,953
(3) Partially Funded
Ortiz Corp
(1) Duration to be determined.
Additional Remarks
None
See B19086 for Water Asset Click Here
See B22105 for Transportation Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 10/01/2024