General Information
B19117 (Water Asset)
Construction of approximately 17,792 linear feet (3.21 mi) of 4, 6, 8,10,12 and 16 inch existing AC Mains with new appropriately sized PVC Water Mains. The project will also install approximately 7700 LF of new Class II Bike Lanes along La Jolla Scenic Drive from La Jolla Village Dr. to Moonridge Dr. The bike lane improvements will include striping only. TEO will provide striping plan. No hardscape improvements will be included.
Jaro, Janice
1
LA JOLLA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $11,412,764
Construction Activity
(1) $8,181,517
(3) Partially Funded
Burtech Pipeline, Incorporated
(1) Duration to be determined.
Additional Remarks
None
See B19105 for Sewer Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024