The City of San Diego Project Information Details
AC Water and Sewer Group 1052A (W)
(Design Build Project)
The City of San Diego
Project Information Details
AC Water and Sewer Group 1052A (W)
(Design Build Project)
Print Page  
General Information
B19166 (Water Asset)
Replacement of approx 9,473 (LF) (1.8 miles) of existing 4, 6, 8, 12 and 16” diameter asbestos cement (AC) distribution mains with Polyvinyl Chloride (PVC) pipes. Abandon 1,878 LF (0.36 miles) of 4, 6, 12 and 16” AC Water mains, Construct approx 493 LF (0.093 miles) of new water pipes including associated water services, fire hydrants, air valves, blowoff, high lining, water main cut-and-plugs and reconnections and other associated work. All water main installation and surface improvements shal
Rubalcava, Eric
8, 4
BARRIO LOGAN, SOUTHEASTERN SAN DIEGO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $7,965,041
Design-Build Activity
(1) $6,135,041
(3) Fully Funded
TC Construction Co., Inc.
(1) 27 Months
Additional Remarks
None
See B19169 for Sewer Asset Click Here
See B24059 for Transportation Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 10/01/2024