The City of San Diego Project Information Details
Sunset Point Comfort Station Imp
(Job Order Contract Project)
The City of San Diego
Project Information Details
Sunset Point Comfort Station Imp
(Job Order Contract Project)
Print Page  
General Information
B19176 (Parks Asset)
This project provides for the replacement of the existing comfort station located in the Sunset Point area of Mission Bay Park off West Mission Bay Drive near the Dana Landing Hotel.
The existing comfort station is to be replaced with a new pre-fabricated comfort station with unisex stalls.
Lozano, Edgar
2
MISSION BAY PARK
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $2,391,000
Construction Activity
(1) $1,649,090
(3) Partially Funded
To Be Selected
(1) Duration to be determined.
Additional Remarks
None
See B19159 for Parks Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 03/01/2024