The City of San Diego Project Information Details
AC Water and Sewer Group 1023B (W)
(Design Bid Build Project)
The City of San Diego
Project Information Details
AC Water and Sewer Group 1023B (W)
(Design Bid Build Project)
Print Page  
General Information
B19205 (Water Asset)
AC Water and Sewer Group 1023B consists of the installation of approximately 4,810 linear feet (0.91 miles) of water main, 486.36 linear feet (0.09 miles) of sewer main, 114.64 linear feet (0.02 miles) of sewer main rehabilitation, water services, fire hydrants, blowoff valves, air vacuum valves, sewer laterals, manholes, curb ramps, pavement resurfacing and all other associated work.
Sleiman, Alex
3
NORTH PARK
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $3,920,724
Construction Activity
(1) $2,184,871
(3) Fully Funded
P K Mechanical System
(1) 20 Months
Additional Remarks
None
See B19204 for Sewer Asset Click Here
See B24076 for Transportation Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 10/01/2024