General Information
|
|
B20014
(Sewer Asset)
|
Rehabilitating approximately 28,909 LF (5.48 mi) of existing sewer mains with necessary point repairs, approximately 23 main point repairs and 10 lateral point repairs, and install 21 clean-outs. The project is located in council district 7, Navajo community.
|
|
Ramos-Banuelos, Jaime
|
|
7
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$4,939,250
|
Construction Activity
|
(1)
|
$2,992,637
|
(3)
|
Fully Funded
|
|
Southwest Pipeline and Trenchless, Inc.
|
(1)
|
39 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|