|
|
Project Information Details
Civic Cntr Plaza Elevator Modernization
(Sole Source Emergency Project)
|
|
Project Information Details
|
Civic Cntr Plaza Elevator Modernization
|
(Sole Source Emergency Project)
|
Print Page
|
General Information
|
|
B20063
(Buildings Asset)
|
The elevators have suffered from an esclating number of entrapments, lurching, and leveling issues; complaints from employees riding the CCP elevators have increased dramatically in the last year. The building was constructed in 1973 and the current elevators are two elevator generations old, Most of the existing equipment is outdated and due to the age, maintenance parts can no longer be found. All six elevators are currently unreliable and require immediate modernization of all equipment. Proj
|
|
Choi, Jong
|
|
3
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$5,065,314
|
Construction Activity
|
(1)
|
$4,045,000
|
(3)
|
Fully Funded
|
|
Otis Elevator Company
|
(1)
|
60 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|