General Information
|
|
B20126
(Water Asset)
|
Replace approximately 7,242 linear feet (LF) (1.37 miles) of existing 8-inch asbestos cement (AC) and 2,549 LF (0.48 miles) of 12-inch AC water mains, including associated water services, fire hydrants, traffic control, etc. Scope also includes curb ramps in all areas impacted by this project. Streets within the project limit will be resurfaced as part of the UU209 & UU629 projects.
|
|
Ramos-Banuelos, Jaime
|
|
9
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$4,963,977
|
Construction Activity
|
(1)
|
$3,588,839
|
(3)
|
Fully Funded
|
|
KTA Construction, Inc.
|
(1)
|
21 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
10/01/2024
|
|
|