General Information
B21042 (Transportation Asset)
This project would replace the 3-inch overlay paving portion of Pacific Beach Pipeline South.
Jaro, Janice
2
MIDWAY-PACIFIC HIGHWAY, PENINSULA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $1,496,688
Construction Activity
(1) $1,496,688
(3) Fully Funded
TC Construction Co., Inc.
(1) 14 Months
Additional Remarks
None
See B21144 for Transportation Asset Click Here
See B12117 for Sewer Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.