The City of San Diego Project Information Details
PWP North City Pure Water Facility Pkg 2
(Design Bid Build Project)
The City of San Diego
Project Information Details
PWP North City Pure Water Facility Pkg 2
(Design Bid Build Project)
Print Page  
General Information
B21058 (Water Asset)
The Pure Water Facility will be constructed north of Eastgate Mall Rd across from the existing Water Reclamation plant. The completed facility will provide the City with a production capacity of 34 million gallons per day (MGD), from which 30 MGD of purified water will be delivered to the Miramar Reservoir. This facility will include an Operations and Maintenance Building, Process Building that will house treatment processes that consists of ozonation, biological activated carbon filtration, mem
Lotfi, Elham
6
UNIVERSITY
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $483,155,004
Construction Activity
(1) $363,220,865
(3) Fully Funded
Shimmick Construction Company, Inc.
(1) 51 Months
Additional Remarks
None
See B15140 for Water Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024