|
|
Project Information Details
PWP NC Wtr Rec Plant Expansion (W)
(Design Bid Build Project)
|
|
Project Information Details
|
PWP NC Wtr Rec Plant Expansion (W)
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B21128
(Water Asset)
|
The North City Water Reclamation Plant (NCWRP) treats wastewater to recycled water standards. To meet the needs of the Pure Water Facility and the recycled water system, NCWRP will need to be expanded. The expansion will increase treatment capacity from 30 MGD to 52 MGD. The major scope elements associated with this project include the construction of a new tertiary filter and improvements to the existing chlorine contact basins.
|
|
Martin, Reyhaneh
|
|
6
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$81,037,361
|
Construction Activity
|
(1)
|
$66,639,949
|
(3)
|
Fully Funded
|
|
Kiewit Infrastructure West Co.
|
(1)
|
64 Months
|
|
|
See B21060 for Sewer Asset
Click Here
|
See S17012 for Sewer Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
12/01/2024
|
|
|