Project Information Details
Sewer and AC Water Group 765 (P)
(Design Bid Build Project)
Project Information Details
Sewer and AC Water Group 765 (P)
(Design Bid Build Project)
Print Page
General Information
Project Identification Number:
B22110
(Transportation Asset)
Project Description:
Overlay surface streets
Contact Person:
Ramos-Banuelos, Jaime
Council District(s):
4
Community Area(s):
SKYLINE-PARADISE HILLS
Project Location Map:
Click Here
Estimated Project Schedule
(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
Estimated Project Dollar Amount
(1)
A. Total Project Cost:
(1)
$947,961
Construction Activity
A. Estimated Construction Contract Amount:
(1)
$947,961
B. Funding Status:
(3)
Fully Funded
C. Contractor:
Ortiz Corp
D. Expected Contract Duration:
(1)
38 Months
Additional Remarks
None
See B17167 for Water Asset
Click Here
See B00369 for Sewer Asset
Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502
Updated As Of:
11/01/2024