The City of San Diego Project Information Details
Balboa Park Pipeline Repl Ph II (P)
(Design Bid Build Project)
The City of San Diego
Project Information Details
Balboa Park Pipeline Repl Ph II (P)
(Design Bid Build Project)
Print Page  
General Information
B22140 (Transportation Asset)
Resurface approximately 1.32 miles of street. Bundled with B17133 Balboa Park Pipeline Repl Ph II (S) and B17140 Balboa Park Pipeline Repl Phase II (W).
Sleiman, Alex
3
BALBOA PARK
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $2,412,632
Construction Activity
(1) $1,957,907
(3) Fully Funded
Ortiz Corp
(1) 38 Months
Additional Remarks
None
See B17133 for Sewer Asset Click Here
See B23017 for Transportation Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 03/01/2024