Project Information Details
Sewer and AC Water GJ 778 (P)
(Design Bid Build Project)
Project Information Details
Sewer and AC Water GJ 778 (P)
(Design Bid Build Project)
Print Page
General Information
Project Identification Number:
B23060
(Transportation Asset)
Project Description:
AC Overlay paving
Contact Person:
Sleiman, Alex
Council District(s):
4
Community Area(s):
ENCANTO NEIGHBORHOODS
Project Location Map:
Click Here
Estimated Project Schedule
(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
Estimated Project Dollar Amount
(1)
A. Total Project Cost:
(1)
$375,665
Construction Activity
A. Estimated Construction Contract Amount:
(1)
$326,665
B. Funding Status:
(3)
Fully Funded
C. Contractor:
TC Construction Co., Inc.
D. Expected Contract Duration:
(1)
89 Months
Additional Remarks
None
See B15069 for Water Asset
Click Here
See B00388 for Sewer Asset
Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502
Updated As Of:
11/01/2024